Technical Specifications for the Sponge Puppet with Mechanism for Storytelling

Product: Sponge Puppet with Mechanism for Storytelling

Project Schedule

Phase Description Duration Key Activities Milestone
Definition & Specifications Gathering requirements and validating needs. 2-3 weeks
  • Identification of functional and non-functional requirements.
  • Feasibility analysis.
  • Research and benchmarking.
  • Definition of success metrics.
Requirements and specifications validated.
Conceptual Design Creation and evaluation of initial concepts. 3-4 weeks
  • Generation of sketches and conceptual models.
  • Analysis of alternatives.
  • Cost and feasibility evaluation.
  • Selection of the best concept.
Final concept approved.
Materialization Design Development of detailed models and technical validation. 4-6 weeks
  • 3D modeling and simulations.
  • Selection of materials and manufacturing processes.
  • Initial testing and adjustments.
  • Cost optimization.
Design ready for detailing.
Detail Design Preparation of final documentation for manufacturing. 4-5 weeks
  • Technical drawings and final specifications.
  • Prototype creation.
  • Functional testing and validation.
  • Preparation for production or implementation.
Final design ready for production.